Start by defining the solar project
A solar power plant project report should explain the proposed generation system, its site and delivery plan, how electricity will be used or sold, and how those assumptions translate into costs and cash flows. A credible report needs project-specific evidence behind each connection.
Record whether the proposal is ground-mounted or rooftop, grid-connected or another arrangement, and whether the commercial model involves sale to a buyer, captive consumption or another defined use. State both MW AC and MWp DC where applicable: the export/inverter capacity and module capacity are not interchangeable.
This guide concerns electricity generation. Solar-cell manufacturing needs a different process, utility and supply-chain assessment; see the manufacturing input checklist.
What a solar power plant DPR should substantiate
| Workstream | Evidence to assemble | Usual input owner |
|---|---|---|
| Project and promoter | Company, ownership, relevant experience, proposed capacity, location and development stage. | Promoter / finance team |
| Land and site | Title or lease records, access, site layout, terrain information and approval status; roof condition and rights for rooftop projects. | Developer / land and technical teams |
| Technical configuration | Module and inverter specifications, AC/DC sizing, layout, electrical arrangement and major scope boundaries. | Designer / EPC contractor |
| Generation assessment | Resource data, model version, loss assumptions and the basis of monthly and annual energy estimates. | Energy assessor / designer |
| Grid and evacuation | Connection correspondence, receiving point, evacuation scope, responsible parties, cost and completion dependencies. | Developer / relevant network utility |
| Offtake or consumption | PPA terms and status where relevant; consumption records and the commercial basis of any proposed savings. | Commercial / consumer team |
| Delivery and operations | EPC scope, procurement milestones, commissioning plan, warranties and O&M responsibilities. | EPC / O&M teams |
| Cost and funding | Dated estimates, exclusions, incurred expenditure, equity plan, borrowing assumptions and model schedules. | Finance / project teams |
Track approvals as obtained, applied for or still to be initiated. Identify the relevant authority and due date for the specific state, site and commercial structure. A Karnataka utility reference in an earlier checklist is not a national requirement.
Connect the generation study to the revenue model
The report should make clear how the energy forecast was produced: weather/resource inputs, equipment assumptions, shading, temperature, electrical losses, availability and degradation treatment. Explain what is included in the energy figure and where it is measured.
Keep gross generation, net export, billed energy and collected revenue distinguishable. For example, a forecast at the inverter output should not silently become electricity delivered at a different settlement point. Use a consistent loss and charge treatment through the model.
For a sale project, document the buyer, tariff basis, term, payment arrangements and agreement status. For a consumption-led project, use relevant demand and billing records, then examine how the proposed generation aligns with consumption. Applicable charges, settlement rules and approvals need project-specific confirmation.
A useful consistency check
If the generation forecast changes, trace the effect into monthly revenue, operating cash and repayment coverage. If grid readiness moves, update the commissioning schedule and construction cash requirements as well. Changing one summary cell is not a revised DPR.
Preparing a 1 MW or 5 MW solar project report
Capacity alone does not determine a complete report. A 5 MW proposal is not automatically five copies of a 1 MW financial model. First clarify whether the stated capacity is AC or DC, then obtain the site and connection evidence for that design.
| Question | What to establish for either capacity |
|---|---|
| Site and layout | Use the actual topography, access, shading and equipment arrangement; do not multiply a generic land allowance. |
| Grid interface | Confirm the receiving point, connection arrangement, evacuation works and responsibilities with the relevant parties. |
| Cost estimate | Price the chosen system and scope. Shared infrastructure, civil works, contracting and equipment choices may change unit costs. |
| Operating case | Use the project’s generation assessment, O&M offer, insurance and replacement assumptions. |
| Financing | Model the actual proposed drawdowns and repayment terms, with commissioning and revenue timing aligned. |
The checklist below works as an input-collection aid for either capacity. It is not a completed 1 MW or 5 MW solar power plant project report.
1 MW solar power plant DPR: a fictional worked example
Teaching example only. Every figure below is a fictional assumption or a calculation from those assumptions. These are not quotations, tariff offers, resource assessments or actual Bitcon assignments, and they do not guarantee project viability or financing.
1. Set the capacity, year and measurement boundary
| Input | Teaching assumption |
|---|---|
| Inverter capacity | 1 MW AC (1,000 kW) combined inverter nameplate capacity. |
| Module capacity | 1.25 MWp DC (1,250 kWp); DC/AC ratio = 1.25. |
| Export limit | 1 MW AC. |
| Operating period | First full non-leap year: 8,760 hours. |
| Gross capacity utilisation factor (CUF) | 22% on the 1,000 kW AC basis, with energy measured at the combined inverter outputs. |
| Separate downstream deduction | 1% of gross energy, covering only auxiliaries and losses between inverter outputs and the settlement meter. |
The assumed 22% gross CUF already incorporates resource, temperature, shading, soiling, DC losses, inverter conversion, clipping and availability up to the inverter outputs. Do not deduct those losses again. The separate 1% applies only to the downstream boundary described above.
2. Calculate annual energy and net CUF
One electricity unit is one kilowatt-hour (kWh). Use 1,000 kW AC in these calculations, not the 1,250 kWp DC module capacity.
| Calculation | Result and basis |
|---|---|
| Gross energy at inverter outputs | 1,000 kW × 8,760 hours × 0.22 = 19,27,200 kWh. |
| Downstream deduction | 19,27,200 × 1% = 19,272 kWh. |
| Net export at settlement meter | 19,27,200 − 19,272 = 19,07,928 kWh, or about 19.08 lakh units. |
| Net AC-basis CUF | 19,07,928 ÷ (1,000 kW × 8,760 hours) × 100 = 21.78%. |
3. Connect exported units to invoices and annual costs
Assume all net exported units are accepted and billed at a fictional ₹3.00/kWh, with no further energy deductions, charges or escalation in this simplified case. Invoice revenue is 19,07,928 × ₹3.00 = ₹57,23,784. Invoicing does not necessarily mean collection; an actual cash-flow model must reflect payment timing and unpaid amounts.
| Item | Annual amount |
|---|---|
| Routine O&M and cleaning | ₹5,00,000 |
| Lease | ₹1,50,000 |
| Insurance and administration | ₹1,50,000 |
| Total listed annual costs | ₹8,00,000 |
| Invoice revenue less listed costs | ₹57,23,784 − ₹8,00,000 = ₹49,23,784 |
₹49,23,784 is before depreciation, financing, tax and capital expenditure. It is not net profit, cash available for debt service or an investment return. This example supplies no capital cost, borrowing, major replacements or lifetime projection, so it cannot establish payback, debt coverage or viability.
Simple sensitivity: 10% lower net export gives 17,17,135.2 kWh. At the same ₹3.00/kWh, invoice revenue is ₹51,51,405.60; less the same ₹8,00,000 costs, the balance is ₹43,51,405.60 on the same limited basis. This is a sensitivity, not a probability forecast.
An actual DPR needs project-specific capital costs, funding and repayment schedules, degradation, major replacements, lifetime projections, collections and applicable charges. Captive consumption needs its own avoided-cost calculation using the consumer’s demand, bills and applicable settlement terms.
Method references, not benchmarks for these figures
The CERC 2024 renewable-energy tariff regulations (definition 2(1)(n)) use inverter nominal AC capacity for solar within their own tariff-determination scope; this is not a universal sizing rule. A SECI tender’s CUF definition (PDF page 434) illustrates why capacity, meter location and annual hours must be stated for the relevant contract; its requirements are not imported into this example. NIWE’s solar-radiation resource assessment work describes location-specific radiation and meteorological data for resource assessment. None of these sources supplies or validates the 22% CUF, 1% deduction, ₹3.00 tariff or costs used here.
Review costs, funding and downside cases together
Reconcile land or lease costs, site development, plant equipment, civil and electrical works, evacuation, pre-operating expenses and other items within the agreed scope. Distinguish quoted prices from allowances, and show inclusions, exclusions, taxes and the estimate date.
Match the funding plan to the expenditure schedule. State how additional costs or delayed revenue would be funded instead of assuming that a contingency line or an uncommitted facility will cover every gap.
- Lower energy delivery: show the effect on revenue and period-by-period debt coverage.
- Delayed commissioning: move the revenue start date and examine the associated construction-period costs.
- Higher capital or operating cost: identify the revised funding need and cash-flow effect.
- Collection or settlement changes: examine working cash requirements using the relevant commercial terms.
Choose plausible scenarios with the technical and finance teams. These are review questions, not forecasts or recommended return thresholds.
A practical eight-part solar DPR outline
Use this outline to organise the evidence and identify gaps. Adapt it to the actual mandate and the recipient’s requirements; completing the sections does not promise approval.
- Executive summary. State the report purpose, assessment date, AC/DC capacity, site, power-use model, total cost and funding need. Reference the supporting schedules and list unresolved assumptions.
- Promoter, site and development status. Attach company and ownership records, relevant experience, land or roof rights, site surveys and access evidence. Record each permission’s status, reference, responsible party and target date.
- Design and generation. Include module and inverter specifications, layouts, the electrical diagram, resource-data sources and model version. Show monthly and annual results, degradation, capacity and meter boundaries, with an auditable loss schedule that avoids double-counting.
- Grid, power-use and settlement arrangements. Include connection correspondence, evacuation scope and dependencies, PPA or consumption records, tariff or avoided-cost basis, metering, applicable charges and payment terms. Distinguish signed agreements from proposals.
- Project costs and implementation. Provide itemised, dated quotations and estimates with quantities, scope, taxes, exclusions, contingencies and expenditure already incurred. Link procurement, construction, grid readiness and commissioning milestones to the spending schedule.
- O&M, warranties and replacements. Attach service scopes and offers, cleaning and maintenance plans, warranty terms and responsibility boundaries. Support insurance, spares and major-replacement allowances with their timing and cost basis.
- Funding and financial projections. Document equity evidence, proposed borrowing terms, drawdowns and repayment schedules. Link monthly energy to bills, collections, operating costs, tax, capital expenditure and cash flows; explain downside cases and how funding gaps would be addressed.
- Risks, open items and supporting records. Maintain a risk and evidence register with source dates, document references, named owners, actions and due dates. Make pending decisions and the limits of the assessment visible.
Before issuing the report, reconcile capacity, dates, energy, costs and commercial and funding terms across the narrative, technical study, quotations, agreements and financial model. Each summary should trace back to the same evidence and assumptions.
Download the solar project input checklist
Use Bitcon’s printable preparation checklist to assemble documents and assign owners before the DPR or TEV appointment. It is adapted from our solar-project working checklist, with historical cut-off dates replaced by the agreed assessment date.
What this download contains: input requests and review prompts. It is not a feasibility conclusion, design certification or completed solar DPR. Project assumptions, technical findings and current requirements must be checked for the actual appointment.
For institutional application forms, consult the intended lender. IREDA’s official forms and checklists provide a reference for applications to IREDA; confirm the current project-specific list with its team.
Solar engineering experience behind the questions
Bitcon’s documented assignments include owner’s engineer / PMC work for the 22 MW AC / 28 MWp DC Rampura project, commissioned in April 2022, and design and detailed engineering for a 4.80 MW AC / 6.72 MWp DC project. Their stated roles are engineering and project support; they are not presented as solar-generation DPR assignments.
For report preparation, explore Bitcon’s DPR service. If the bank instead requires independent appraisal, review the TEV appointment scope.
Solar report questions
Can a generic solar report PDF be submitted for funding?
It can illustrate a structure, but the lender needs evidence about the actual project, promoter, site, technology, offtake, costs and proposed financing. Confirm its required scope and consultant appointment.
Can I use one per-MW cost for every site?
A benchmark can help screen an early idea. A DPR needs a project-specific estimate with dated quotations and clear scope, including infrastructure and costs outside the main EPC package.
Is the checklist a list of every statutory approval?
No. It helps collect information. The applicable permissions and current technical requirements depend on the location, configuration and commercial model; confirm them with the relevant authorities and specialists.